UPDATE: Edgecomb Route 1 construction’s temporary traffic pattern begins Aug 23
UPDATE: The beginning date of the closure has changed from August 16 to August 23.
EDGECOMB — The Maine Department of Transportation wants members of the traveling public to be aware of changing traffic patterns at the intersection of Route 1 and Route 27 (Boothbay Road) in Edgecomb. Beginning Monday, Aug. 16, 2021, northbound Route 27 traffic will be detoured to Cross Road in order to access Route 1.
“We expect this detour to be in place until early September,” said MDOT, in a news release. “We continue to ask members of the traveling public to be patient and extremely careful when navigating this intersection.”
The contractor on this project is Sargent Corporation of Old Town. The contract amount is $2,346,703. The project is still scheduled to be finished by mid-October.